This article explains how to complete an individual task from start to finish:
- add an activity to describe the intervention, add or record the spare parts used and enter a meter reading,
- complete a checklist if one is available,
- review related information (equipment, technician, entered data),
- mark the task as completed or reopen it if needed.
The users assigned to the task are responsible for its completion.
Creating the Activity
Available for
- Roles: Administrator, Technician, Provider (if assigned to a task)
- Plans: Premium, Advanced, Enterprise
To describe the intervention they carried out, users must add an activity from the task page, enriching the work order until the intervention is resolved.
An activity allows for:
- Describing the intervention performed
- Specifying the time spent on the intervention
- Noting the presence of an external provider or contractor
- Recording the spare parts used during the intervention
- Adding meter readings
A participant can also attach any technical or administrative documents related to the task, or any other essential documents for the proper execution of the intervention.
For more information, please consult this article.
Completing a Checklist
Available for
- Roles: Administrator, Technician, Production, Service Provider
- Plans: Premium, Advanced, Enterprise
Some tasks include a checklist. When one is present, the checklist ensures that all essential steps are followed, reducing the risk of missing items and improving the quality of operations.
You can complete a checklist by clicking the Start button. This will open the checklist modal, with all the steps to be filled out.
As soon as the checklist is started, the task switches to the In Progress status (or Late and Started if its scheduled date has passed), even if no activity has been added yet. Your answers are saved immediately, as you enter them.
If you only wish to view the checklist without starting the task execution (and thus without changing the task status), you can click the Preview button.
How to Mark an Individual Task as Completed?
Available for
- Roles: Administrator, Technician, Production (if assigned), Service Provider (if assigned)
- Plans: Premium, Advanced, Enterprise
Once the user has completed the intervention, they can mark the task as completed. To validate, close or complete a task, click the Mark as completed button at the top right of the page. Once marked as completed, the task can no longer be modified. Only the network administrator will be able to reopen the task.
Note: if your network has enabled the mandatory creation of a linked task, a mandatory validation step answered non-compliant (thumbs down) requires you to create a task from that step, using the Create Task button, before you can complete the task. For details, see How to complete a checklist?
Note: if your network requires a complete checklist before closure (feature enabled on request), completing a task whose mandatory checklist steps are not filled in displays a warning or is refused, depending on the network setting. For details, see Why can't I close a maintenance plan task?
Note: This process is different for tasks belonging to a maintenance plan. For details on these types of tasks, please refer to this article.
How to Mark an Individual Task as Incomplete?
Available for
- Roles: Administrator
- Plans: Premium, Advanced, Enterprise
Once a task is marked as completed, it can no longer be modified or updated with additional activities.
However, if a modification is necessary, the network administrator can mark the task as incomplete by using the button that appears.
Note: This process is different for tasks belonging to a maintenance plan. For details on these types of tasks, please refer to this article.